Fire curtain installation in a high-rise residential building

SUPPORT · US CARE®

U.S. CARE® — Fire Curtain Inspection and Maintenance

PER NFPA 80, CHAPTER 22 & MANUFACTURER'S OPERATING AND MAINTENANCE GUIDELINES

NFPA 80 requires opening protectives to be inspected and tested annually — a deployed-and-verified drop test, not a visual check. U.S. CARE® is our preventative maintenance program: scheduled inspections, drop testing, and documentation for your AHJ, performed by the people who built the system.

— PROGRAM SCOPE

What the program includes

  • Annual drop test
  • Motor and controller check
  • Fabric and bottom bar inspection
  • Sensor verification
  • Written compliance report

PROGRAM TIERS AND PRICING IN PREPARATION — CONFIRM SCOPE AT EXT. 101

— CODE

Why annual inspection is not optional

NFPA 80, Chapter 22, and the manufacturer's operating and maintenance guidelines require it, and your AHJ will ask for the documentation. A deployed-and-verified drop test with a written report is what satisfies both.

— SERVICE DETAIL

Our 39-point electrical and mechanical service includes

  1. 01Check all fuses
  2. 02Check back-up power supply
  3. 03Check voltage at MC positive loop at CP — retracted state
  4. 04Check voltage at MC positive loop at CP at deployment
  5. 05Check voltage at MC negative loop at CP — retracted state
  6. 06Check voltage at MC negative loop at CP at deployment
  7. 07Check motor supply in / out at MC out
  8. 08Check line voltage supply in / out
  9. 09Check transformed voltage & transformer — retracted state
  10. 10Check transformed voltage & transformer at deployment
  11. 11Check voltage at CP — retracted state
  12. 12Check voltage at CP at deployment
  13. 13Check loop voltage for short degradation
  14. 14Test key switch contact to fire alarm circuit
  15. 15Check delayed reset control
  16. 16Check mains failure, all trouble lights & annunciator
  17. 17Check (Bldg. Mgmt. System) BMS
  18. 18Spray anti-static printed circuit board (PCB)
  19. 19Spray PCB board for dust collection
  20. 20Test override & test grounds
  21. 21Check accessible wiring terminations
  22. 22Grease all contacts
  23. 23Lubricate side rails & housing — check for obstruction
  24. 24Adjust curtain fabric tabs and bottom bar
  25. 25Inspect curtain fabric for damage
  26. 26Inspect bottom bar for damage
  27. 27Inspect push buttons for damage
  28. 28Bottom bar fabric slack removed
  29. 29Obstruction of bottom bar
  30. 30Bottom bar sits flush with headbox
  31. 31Obstruction of headbox
  32. 32Obstruction of side rails — opening must be no less than 1/2 inch
  33. 33Apply fire coating as necessary
  34. 34Verify all labels are installed in the correct locations
  35. 35Cycle curtain system for efficient and safe operation per NFPA 80 guidelines
  36. 36Curtain deployment test — Cycle 1
  37. 37Curtain retraction test — Cycle 1
  38. 38Curtain deployment test — Cycle 2
  39. 39Curtain retraction test — Cycle 2